13 oil gas projects were
scheduled to start production capacity of all the projects was 954 million
cubic feet per day [mmfcfd] or 194,121 barrels of oil day. The Oil-gas Upstream
Activity Execution special task force SKK Migas] had their commitment to
accomplish the project on time.
“If there is any project behind schedule they would
affect the volume of lifting of oil-gas this year,” Head of SKK Migas Public
Relations Dept Elan Biantoro disclosed in Jakarta on Sunday [5/1].
Some projects to start production were among others: Sisi
Nubi 2B , Block Nahakan with Total E&P Indonesia which was targeted to
produce 350 mmfd in quarter 1 2014. Furthermore development of Senoro gas with
operator JOB Pertamina-Medco Tomori Sulawesi was planned to start o produce 8
mmscfd and 250 barrel of oil per day in quarter 3.
Three projects which were targeted to start production in
2013 last would start production in quarter 1/2024. The three projects were:
Ridho field run by contractor Odira Energy Karang Agung producing 1,200 barrel
of oil per day. The Gundih which was developed by Pertamina EP produced 50
mmcfd and 600 barrels of oil per day, and Bayan A project with contractor
Manhattan Kalimantan Investment produced 50 mmscfd and 250 barrels of oil per
day.
Elan disclosed that there were 3 projects having full
attention of SKK Migas in regard to the high production output and challenges
faced. The first one was Bukit Tua field, Block Ketapang 2 with Petronas
Carigali acting as contractor. The project was projected to produce 70 mmscfd
and 20,000 barrels of oil per day in quarter 4 of 2014. One thing to be
observed was the process of negotiation of gas price and change of candidate
buyer. Besides this project was based on upstream and downstream scenario so
there were some strategic policy beyond the authority of SKK Migas.
The same was happening in Muriah field, block Kepondang
also operate by Petronas. This project producing 116 mmcfd depended on the
completion of gas pipelining project at the downstream “Construction on the
upstream facilities would be ready by October 2014,” Elan remarked.
The last project was the Banyu Urip Field, Block Cepu run
by contractor Mobil Cepu Ltd [MCL]. This strategic project was scheduled to
produce in quarter 4 2014 with peak production of 165,000 barrels per day. Some
challenges to face was social economic problem and lateness in engineering,
procuring, and construction of facilities. “The projects must be intensively
safeguarded to keep on schedule” Elan concluded.
The effort to ensure that this oil–gas project would
produce on time was among others supervision and control through monthly
meeting for monitoring and three monthly meeting with all related parties,
including visit to the fields. (SS)
Business News - January 10, 2014
No comments:
Post a Comment